PROCUREMENT FOR OLKILUOTO 3
Structure of the project

1. Overview

On December 18, 2003, TVO signed two contracts:

- The turnkey plant construction contract with the Olkiluoto 3 Consortium set up between Framatome ANP GmbH, Germany, Framatome ANP S.A.S., France and Siemens AG. The Supplier may to his discretion in his material use "the AREVA Group" when meaning Framatome ANP GmbH, Germany and Framatome ANP S.A.S., France."

The leader of the consortium is Framatome ANP GmbH

- The fuel contract with Framatome ANP GmbH for the supply of the first core.


2. Roles and work scope of TVO, FANP and Siemens in the construction of OL 3

Scope of Owner TVO
  • Leader of the licensing process with the Finnish Government and safety authority (STUK)
  • Site preparation, excavation
  • Switchyard, raw water intake and outlet, quay, office building and other ancillary buildings
Scope of the Consortium (CFS)
  • Supply of the Olkiluoto 3 NPP on a turn-key basis
  • Responsibility for the overall project co-ordination as well as functional and technical integration of the complete plant

Within the Consortium the Scope of Supply is divided as follows:

Scope of Framatome ANP
  • Complete Nuclear Island (NSSS and BNI)
  • Civil works for the complete Nuclear Island
  • The plant simulator
  • Supply of the first core
Siemens AG
  • Complete Turbine Island
  • Balance-of-Plant systems
  • Civil works for the complete Turbine Island

Purchasing / Trades

There will be Information about the trades which have to be offered. To help subsuppliers to come into contact with the consortium the linked pages will show how to prepare prequalifications and bids. The "Purchasing Management" is resposible for the subsuppliers offers.


Technical Information

Further there will be information about the technology, I & C and the quality of the new NPP.